A math question. help.?

0 votes

8 men and 12 boys can do a peice of work in 10 days while 6 men and 8 boys can do the job in 14 days. In how much time can one man do the job.? Please help. How did you solve it?

asked Jul 5, 2014 in ALGEBRA 2 by anonymous

1 Answer

0 votes

8 men and 12 boys can do a peice of work in 10 days.

8M + 12B = 1/10

80M + 120B = 1  -> (1)

In one day 80 men and 120B can complete the job.

6 men and 8 boys can do the job in 14 days.

6M + 8B = 1/14

84M + 112B = 1  -> (2)

In one day 84 men and 112B can complete the job.

Solve equation(1) and equation(2).

80M + 120B = 84M + 112B

120B - 112B = 84M - 80M

8B = 4M

2B = 1M

B =1/2 M

Substitute M value in equation (1).

80M + 120(1/2 M) = 1

80M + 60M = 1

140M = 1

M =1/140

A man can do the job in 140 days.

 

 

 

answered Jul 5, 2014 by joly Scholar